Schafer road deviation

As part of the construction of the western aqueduct, a 1m diameter water supply pipe is in the process of being installed along the southern carriageway of Qashana huzwayo Road, between Blase Road and Henred Road. This requires the temporary closure of one lane at the Schafer Road intersection. Traffic access from Schafer Road to Qashana Khuzwayo Road will be controlled at the traffic light via a stop and go system.

For more information please visit: https://godurban.co.za/category/media/


12

June

2015

Road deviation Hendred road

A 1m diameter water pipe is in the process of being installed along the southern carriageway of Qashana Khuzwayo road between Blase Road and Henred Road. As a result, Hendred Road will be closed to traffic from Qashana Khuzwayo Road. Access to Hendred Road will only be available via a detour through Otto Volek Road and Frans Volek Road

For more information please visit: https://godurban.co.za/category/media/


12

June

2015

Oppenheimer road deviations

As part of the GO!Durban’s Integrated Rapid Public Transport Network through Pinetown, a number of temporary deviations along Josiah Gumede Road, Beviss Road and Qashana Khuzwayo Road are scheduled to take place. Please note that construction will be taking place at the Beviss/ Oppeneheimer intersection. Oppenheimer Street will not be accessible from Beviss Road. Motorists are requested to use Suffert Road to access Oppenheimer Street and Devon Road.

For more information visit: https://godurban.co.za/category/media/


9

April

2015

GO!Durban moves ahead in 2015

The eThekwini Municipality’s GO!Durban (IRPTN) Integrated Rapid Public Transport Network, possibly one of the largest service delivery projects in the transport sector ever undertaken in South Africa “will continue to progress at a rapid pace in 2015,” says Head of the eThekwini Transport Authority, Thami Manyathi.

GO!Durban began rolling out major milestones in 2014 which included the awarding of five major construction tenders, the signing of an MOA with the leadership of the mini-bus taxi industry, the unveiling of the project’s Empowerment Charter, the launch of the city’s NMT (Non-Motorised Transport Network), the consolidation of the cashless MUVO smartcard system, engagements with community stakeholders, businesses and the eThekwini citizens, as well as the launch of a mobile marketing bus and other key brand awareness events.

For more details click here.


Corovoca Rail Bridge, Duffs Road, Avoca Hills, Durban, eThekwini
23

March

2015

Active deviations in Avoca Hills

As part of the delivery of GO!Durban the city’s new integrated rapid public transport network, construction work has begun on widening the Corovoca Rail Bridge between Duffs Road interchange and the Avoca Hills intersection.

Stefanutti Stocks JV Construction have been appointed to develop a portion of this route which is approximately 4.4km long and extends along the MR577 from south of the Duffs Road interchange to the east of the MR577/Inanda Road intersection. Included in the scope of work is the widening of Corovoca Rail Bridge north of Avoca Hills intersection.

Deviations which will be active until the end of November 2015 are as follows: From the Avoca Hills intersection, north bound traffic will be diverted to the outer – west lane of the South bound carriageway until Lark road intersection. Traffic will then be diverted back to the north bound carriageway at the Lark road intersection as per the existing conditions – to normalise the situation.

For more click here.


durban, go!durban, Newlands, Durban, KZN
10

March

2015

Newlands Expressway Interchange

The eThekwini Municipality is in the process of dramatically improving public transport within the City of Durban. The overall goal is to improve the quality of life for the citizens of Durban through the construction of a world class integrated rapid public transport network (IRPTN). Forming part of the network is Route C3, which will connect the areas of Bridge City, KwaMashu and Pinetown with one another.

Group Five/PANDEV JV Construction have been appointed for the construction of a portion of IRPTN Route C3. This section is approximately 4.5km long and extends along MR577 from just west of the Umgeni viaduct to the east of the MR577/Inanda Road intersection. Included in the scope of works is the construction of Newlands Expressway Interchange. The proposed Newlands Expressway Interchange is situated nearby the existing MR577/Newlands Expressway intersection. The proposed interchange will replace the existing intersection when complete and will include three ramps and a bridge.

The total construction period of the contract will extend for an estimated 23 months. Construction on the Inanda Road/MR577 intersection commenced on 26 May 2014. Construction for the MR577/Newlands Expressway Interchange commenced on 9 February 2015.


Qashana Khuzwayo Road, durban, kwazulu natal, go durban
26

January

2015

Road deviation along Qashana Khuzwayo Road

As part of GO!Durban’s initiative to provide a more efficient, safer and faster public transport service for the citizens of our city, the eThekwini Municipality is currently constructing a section of the Integrated Rapid Public Transport Network (IRPTN) through Pinetown and New Germany. This requires that from Monday, 26 January 2015, Northbound and Southbound traffic on Qashana Khuzwayo Road (Shepstone Road) will be diverted along Blasé, Chelsea Avenue and Escom Roads. Access to the shops and businesses on Qashana Khuzwayo will be from Regent Street.

This deviation was originally scheduled to take place on Monday, 19 January 2015 but was postponed and will now take place on Monday, 26 January 2015.

It is anticipated that the detour will be in operation for approximately 3 months.

The City greatly appreciates your patience in this regard and apologises for any inconvenience this may cause.

For further information on this specific construction work call 073 293 5144.